WFC Timeline

2010
Facility Acquisition
Facility Acquisition
  • SIP acquired from ArcelorMittal in 2010
  • Beginning of site remediation and demolition
2011
Site Marketing and Planning
Site Marketing and Planning
  • Strategic planning and marketing efforts to make the site available to industrial activity

2014
Leasing Efforts Increase
Leasing Efforts Increase
  • SIP begins to welcome industrial tenant activity
  • 100+ developable acres made ready
2018
Significant Tenant Activity
Significant Tenant Activity
  • Tenant roster passes 15 active leases
  • Additional developable land available
2021
Available Property
Available Property
  • Over 100 land acres and 400k sq. ft of contiguous building area available
  • 3+ MW Solar Project planned for site
  • Over 15 current industrial tenants